e Integrated Program Management Report (IMPR), what is the cost performance index (CPI) for the Cooling System Work Breakdown Structure (WBS) element?…

 Using the cumulative data provided from the Integrated Program Management Report (IMPR), what is the cost performance index (CPI) for the Cooling System Work Breakdown Structure (WBS) element?

(IMAGE DESCRIPTION: WBS number 1.1.3.10, Cooling System, has a BCWS of 1830, a BCWP of 1444, an ACWP of 1973, a BAC of 2291, and an EAC of 2706.)